Sellafield Vault Yields Nuclear Secrets

UK Gov

Sellafield Vault Yields Nuclear Secrets

One of the most challenging puzzles in the UK’s nuclear clean-up programme is being solved.

Waste is now being routinely retrieved from one of the world’s oldest nuclear waste stores for the first time in its history.

Sellafield’s Pile Fuel Cladding Silo has effectively been a locked vault since the 1970s. That was when waste stopped being tipped into its 6 compartments.

After decades of work to figure out how to take waste from a building designed never to be emptied, retrievals teams are now doing exactly that.

So far, enough waste to fill 18 storage boxes has been cleared.

And some of the items recovered are not what you’d expect in an intermediate level nuclear waste store.

Among them is a 1960s Electrolux vacuum cleaner.

It’s believed the household hoover was used to suck up dust in the facility during its operational life in the 1950s and 60s.

Because the dust was radioactive, when the vacuum was no longer needed, the only place to dispose of it was in the silo itself.

The 1960s Electrolux vacuum cleaner discovered in Sellafield’s Pile Fuel Cladding Store

Roddy Miller, Sellafield Ltd’s chief operating officer, said:

It’s a fantastic achievement to get to the point where we’re routinely retrieving waste from the building.

The scale of the challenge was immense. Remember, this was a facility that was not designed to be emptied.

The vacuum cleaner is a great example of how challenging it is to clear this silo. We don’t know for sure what’s in there. They didn’t keep accurate records in those days.

Anything taken into the building by the workforce of the day was likely to be contaminated because of the environment they were working in.

There was no alternative disposal route for contaminated material, so everything just went into the silo.

Ironically, a modern-day vacuum cleaner is also playing a part in the waste removal job, sucking up dust created when waste is dropped into storage boxes. It will eventually be consigned as waste itself, joining its 1960s predecessor.

Removing waste from old buildings like the Pile Fuel Cladding Silo is Sellafield’s most important job today.

Alongside it, there’s another silo and 2 ponds that need to be emptied. The ponds store used nuclear fuel underwater and were also not designed to be emptied.

Each one of these buildings needs its own unique decommissioning plan. All of them will take decades to complete.

You can

https://www.gov.uk/government/news/sellafields-locked-vault-gives-up-its-nuclear-secrets

View Original | AusPol.co Disclaimer

Have Your Say

We acknowledge and pay our respects to the Traditional Owners of country throughout Australia


Disclaimer | Contact Us | AusPol Forum
All rights are owned by their respective owners
Terms & Conditions of Use